On August 25, 2016, Unit 1 of Xekaman 1 Hydropower Plant successfully joined Vietnam’s Grid
Song Da Coporation is the EPC General Contractor of Xekaman 1 Hydropower Project (HPP) and 230kV transmission line from Xekaman 1 HPP to Bo Y – Kon Tum border gate.
At 3:27PM, August 28, 2016, Unit 1 of Xekaman 1 Hydropower Plant experienced 72 hour commissioning, officially joining the grid to Vietnam.
At 3:44 PM, August 26, 2016, load shedding of Unit 1 of Xekaman 1 Hydropower Plant was completely done.
LOAD SHEDDING OF XEKAMAN 1 HYDROPOWER PLANT COMPLETELY DONE
At 3:44 PM, August 26, 2016, load shedding of Unit 1 of Xekaman 1 Hydropower Plant was completely done.